Sudan’s energy ministry is working with Chinese firm Siyuan Energy Company to supply transformers and mobile power stations to repair infrastructure damaged by the country’s civil war, a ministry statement said on Tuesday. The electricity sector has suffered extensive damage in the 20-month conflict, with approximately 150,000 kilometres of transmission lines and 15,000 transformers affected, according to ministry figures. Key power stations in Bahri, Garri and Jebel Aulia have also been severely damaged. Consulting Engineer Mu’tasim Ibrahim Ahmed met the regional director of Siyuan Energy Company in Cairo on Tuesday to discuss accelerating the delivery of hydroelectric generation transformers, the statement said. Both sides agreed the Chinese company would conduct field assessments of war-damaged stations in Sudan and urgently supply emergency mobile transformation stations to provide immediate relief, it added. They also discussed adding more transformers to their agreement. (Sudan Tribune)