Monday, September 15, 2025
Home Blog Page 34

Customs Commission’s delay on origin verification guideline causes revenue losses, operational inefficiencies

0

The Ethiopian Customs Commission’s prolonged failure to approve the Origin Verification Guideline (OVG) has led to significant government revenue losses and reduced operational efficiency, according to a recent audit report. The draft guideline, designed to streamline customs procedures and ensure appropriate tariffs are applied by verifying the country of origin of imports, has remained pending for over a year without formal approval or implementation.

The absence of a clear framework for origin verification has disrupted tariff reforms, causing procedural bottlenecks that resulted in both uncollected taxes and inflated tax burdens. The Tariff Classification and Country of Origin Directorate completed the draft OVG in the 2023/24 fiscal year and submitted it to the Customs Operations Sector. However, despite the elapsed time, the directive has neither been reviewed nor disseminated to branch offices for enforcement.

The audit highlighted how this inaction has impaired the efficiency of tax collection in key sectors such as agriculture, directly affecting the national treasury’s revenue intake. While Commission officials cited the need to incorporate recent African Continental Free Trade Area (AfCFTA) implementation rules into the guideline as justification for the delay, the Federal Auditor General’s office rejected this rationale. The auditors argued that pending improvements should not have stalled the immediate approval and implementation of the directive.

Questions about the Commission’s internal processes were further raised, as officials claimed to have verified the authenticity of 212 origin certificates between fiscal years 2014 and 2016 EC but failed to provide documentary evidence to substantiate these claims.

The report also criticized the Commission’s failure to fully leverage technology and improve inter-agency collaboration. While plans exist to link Ethiopia’s electronic single-window customs system with counterparts in Kenya, Djibouti, and other COMESA member states, progress remains limited to preliminary contract negotiations, with no tangible results achieved.

Moreover, the Commission has yet to fully implement its electronic tariff book system or integrate its single-window platform with key government bodies such as the Ministry of Agriculture, Ministry of Industry, and the Investment Commission—missing critical opportunities for streamlined and efficient customs operations.

The audit concluded that these unfulfilled technological initiatives have rendered Ethiopia’s customs processes technologically outdated and inefficient, hampering trade facilitation and revenue generation.

The Ethiopian Customs Commission now faces mounting pressure to expedite the approval and operationalization of the Origin Verification Guideline and to embrace digital modernization to support economic growth and ensure effective tariff collection in line with regional trade commitments.

Regulatory hurdles delay distribution of approved GM Maize

0

A dispute has emerged between a regulatory body and a national research institute regarding the conditions for releasing recently approved genetically modified (GM) maize, as seed companies begin planting.

Ethiopia made a historic decision in March to approve the commercial release of insect-protected TELA maize varieties after seven years of rigorous research and testing.

The National Variety Release Committee (NVRC) granted approval for these genetically modified varieties, which are designed for insect resistance and drought tolerance.

However, Tesfaye Disasa, PhD, the TELA Maize project country coordinator at the Ethiopian Institute of Agricultural Research (EIAR), has voiced significant frustration over delays in making the seeds available to farmers.

“Every new technology requires a vital testing period, but in our experience, we are often slow to adopt them,” he told Capital. While the seven-year approval process for the GM maize was thorough, he believes such a lengthy delay is unnecessary.

Tesfaye pointed to protracted procedures in agencies outside the agricultural research institute as obstacles to the timely distribution of this potentially transformative seed variety.

“This farming season, we had planned to use 120 agricultural demonstration plots to showcase the technology for farmers. Unfortunately, this was impossible due to very limited seed multiplication,” he explained.

He identified the main challenge as the restrictive terms and conditions imposed by the Environmental Protection Authority (EPA) as part of the approval process. Tesfaye argued that the requirements regarding specific growing zones, reproductive isolation, and the use of isogenic maize lines as a “refuge” are impractical.

Experts in the sector agree, stating that these conditions unnecessarily limit seed distribution and infringe upon farmers’ rights.

They contend that enforcing such agricultural regulations falls outside the EPA’s mandate and is more a matter of personal opinion than legal authority.

They argue that once the EPA grants environmental release approval, subsequent issues of seed multiplication and distribution should be managed by the Ministry of Agriculture in alignment with farmers’ interests.

“Unless the EPA changes its conditions, it may delay the adequate availability of seeds for farmers by another year,” the experts cautioned.

Tesfaye noted that such restrictive practices are not present in the 35 other countries that have adopted similar GM technologies. “We are currently working to persuade the authority and other relevant government bodies to lift these preconditions. I remain hopeful that they will amend them,” he said.

EIAR is currently conducting demonstration farming to showcase new seed technology to seed companies and farmers, rather than implementing full-scale multiplication.

Several organizations, including MIDROC, Luna, the International Livestock Research Institute, and Ethio Vegfru, are testing the new seeds on their own plots.

“Our goal is to expand seed access to farmers in the near future,” Tesfaye stated. EIAR is also conducting demonstrations at its research sites in Melkasa, Dera, and Mieso.

The approved varieties—WE3106B (insect-protected) and WE7210B and WE8216B (insect-protected and drought-tolerant)—were developed through the public-private TELA Maize project.

These varieties are designed to protect against destructive pests like stem borers and fall armyworms, which have long troubled Ethiopian farmers.

These new varieties offer a yield advantage of up to 60% over conventional maize. Experts emphasize that the transgenic maize improves grain quality, reduces the reliance on chemical insecticides, lowers production costs, and minimizes environmental and health risks.

Tesfaye described the commercial approval as a significant milestone for Ethiopian agriculture. The TELA maize seed will be available to smallholder farmers royalty-free through local seed companies, potentially saving farmers at least USD 750 per hectare in pesticide costs.

Additionally, the NVRC has approved the release of Bt-GT cotton, engineered to withstand bollworms, a major pest affecting cotton crops. This approval is crucial for Ethiopia’s textile sector, which is projected to demand 200,000 metric tons annually within two years—far exceeding the current domestic production of 50,000 metric tons.

Field trials indicate that the GM cotton yields between 48-57 quintals per hectare, significantly higher than the 32 quintals from local varieties.

The adoption of these GM crops aligns with Ethiopia’s 15-year National Cotton Development Strategy, aimed at producing 1.1 million metric tons of cotton and generating up to USD 125 million in annual export revenue. This initiative is part of a broader effort to position Ethiopia as a leader in Africa’s textile industry and to combat the issue of illegally imported unregulated seeds.

Experts believe that the commercial release of TELA maize and Bt-GT cotton marks a transformative moment for Ethiopia’s agricultural sector.

Public projects plagued by over 17 billion birr in mismanagement, waste

0

A recent audit report by the Office of the Federal Auditor General (OFAG) has uncovered widespread financial mismanagement, delays, and inefficiencies in the country’s public projects, resulting in losses exceeding 17 billion birr (approximately $121.4 million) in road construction and university developments alone.

The report details systemic issues affecting government-funded projects, with over 180 road projects incurring more than 13.26 billion birr in cost overruns in addition to their initial budgets. This means that more than 75% of these projects have faced significant additional costs caused by delays, overbudgeting, and poor management practices.

The problem extends beyond infrastructure to other vital sectors such as electricity generation, irrigation, and higher education projects. The audit found that many projects were not completed on schedule, leading to wasteful spending and stalled development efforts.

Officials from the Ministry of Planning and Development (MoPD) attributed these challenges to several factors, including difficulties in land acquisition and boundary enforcement, ongoing security concerns, disrupted financial flows, design changes, inflationary pressures, foreign exchange shortages, and the limited capacity of contractors.

Further compounding the issue, the audit revealed that funds disbursed between 2020 and 2024/25 were sometimes allocated to projects that either failed to commence or should have been completed earlier, highlighting glaring gaps in project monitoring and management.

Significantly, the report exposes grave financial irregularities and embezzlement at several universities, including Addis Ababa University, Dire Dawa University, Wolaita Sodo University, Wachemo University, and Haramaya University.

For instance, Addis Ababa University received over 437 million birr for 13 projects—such as a student dormitory, renovations at the Yared School of Music, and a café upgrade—that never started and for which funds were not returned. Similarly, Dire Dawa University was allocated nearly 603 million birr for various construction projects from 2021 to 2024, including an 11 million birr advance for a guest house, yet work had not begun.

The situation is echoed at Haramaya University and Wolaita Sodo University, with allocations of 90.4 million birr and 333.6 million birr, respectively, for incomplete projects.

Moreover, the audit found that more than 2.9 billion birr was paid for projects at universities that had already been completed—1.4 billion birr at Wolaita Sodo and over 1.8 billion birr at Wachemo University—representing funds spent without proper justification or return.

The report also highlighted over 1.11 billion birr allocated for five universities’ projects that were diverted for purposes other than their original intent, underscoring a lack of accountability.

In total, the audit identified around 4.74 billion birr disbursed for either completed or unstarted projects across multiple universities, funds which have yet to be reimbursed.

The Federal Auditor General has urged urgent reforms to establish a robust project management and monitoring system to safeguard public resources and improve efficiency. Recommended measures include implementing a modern, technology-driven information system to track projects from initiation to completion, ensuring mandatory environmental and research assessments before project commencement, and improving oversight to prevent misuse of funds.

The Auditor General further emphasized the need for stringent accountability mechanisms targeting individuals responsible for financial mismanagement and called for sustained capacity building and technical support for project implementers across all levels.

China’s Unwavering Commitment toHigh‑Level Opening‑Up

0

In today’s world, economic development faces multiple challenges. The technological, digital, and intelligence divides continue to widen, and structural problems such as the growing gap between developed and developing countries and the marginalization of the least developed countries are becoming increasingly prominent.


Against this backdrop, China is demonstrating its responsibility as a major power through concrete actions. At the recently concluded 2025 World Artificial Intelligence (AI) Conference, China released the Global AI Governance Action Plan, calling for international cooperation and coordinated governance to promote the accessibility and benefits of AI for all. The upcoming 8th China International Import Expo in November this year will establish a dedicated exhibition area for products from least developed countries (LDCs) for the first time, and expand the African Products Exhibition Area, creating convenient channels for products from Global South countries to enter the Chinese market.


However, in disregard of the facts, some Western media hype up the so-called “overcapacity,” “industrial subsidies,” and “export dependence” against China, putting forward the false proposition of “economic rebalancing.” Facts speak louder than words. China’s practice of innovation and opening up is a powerful rebutted to these false accusations.


China’s new energy capacity is advanced capacity that can bridge the world’s “green gap.” The current global new energy capacity falls far short of market demand. The International Energy Agency estimated that global demand for new energy vehicles (NEVs) will reach 45 million units by 2030, over four times the 2022 level, resulting in a demand gap of 27 million units. As the world’s largest NEV producer, consumer and exporter, China is becoming the core pillar filling the gap. In 2024, China produced 12.89 million and sold 12.87 million NEVs respectively, with exports surpassing 2 million for the first time, while over 10 million units served the domestic market. By deeply integrating green technological innovation into the national innovation system, China has made breakthroughs in key technologies such as photovoltaic cell efficiency and NEV manufacturing, significantly reducing costs and laying a solid foundation for the global diffusion of clean energy and green technologies.


The core competitiveness of “Intelligent Manufacturing in China” stems from the innovation strength of Chinese enterprises fostering new quality productive forces. Driven by innovation, China is accelerating the development of new quality productive forces. In the first half of 2025, the value-added output of large-scale high-tech manufacturing increased by 9.5% year-on-year. The production of cutting-edge products such as 3D printing equipments, NEVs, and industrial robots surged by 43.1%, 36.2%, and 35.6% respectively compared with the same period last year. Backed by continuous technological innovation, robust supply chains, and fierce market competition, “Intelligent Manufacturing in China” have gained widespread popularity in global markets, which is the result of the industrious effort of Chinese enterprises. In 2024, China’s total research and development (R&D) expenditure reached 3.6 trillion yuan, ranking second in the world, among which 77% comes from Chinese enterprises investment. China also leads the world in total R&D personnel and science and technology professionals, and it boasts the largest number of top 100 innovation clusters globally, with more than 460,000 high-tech companies. Fundamentally, China’s industrial competitiveness reflects its innovation capability.


China, leveraging its super large-scale market, is creating shared opportunities for the world. With its super large-scale marke, China’s domestic demand is the main engine and anchor of economic growth. Among the hundreds of thousands of Chinese companies that actually exported goods in 2024, nearly 85% also engaged in domestic sales, which accounts for nearly 75% of total sales. The international market is an extension of the domestic market, with the robust domestic circulation providing a solid foundation for the dual circulation development paradigm. On December 1, 2024, China has granted zero-tariff treatment to all LDCs with which it has diplomatic relations, including 33 African nations, on 100% of their products. By March 2025, China’s imports from African LDCs had reached USD 21.42 billion, marking a 15.2 percent year-on-year increase. In June this year, China further announced its readiness to extend the zero-tariff treatment to cover 100% of tariff lines for all 53 African countries that have diplomatic ties with China, and give African LDCs more export access facilitation. China is thus creating more opportunities for Africa and the world through tangible actions.


China’s path of economic innovation is both a journey of self-reliance and determined striving, rooted in its own strengths, and an open road of embracing the world and pursuing win-win cooperation. China’s success stems from market reforms, technological innovation, and high‑level opening‑up. Narratives such as “overcapacity,” “industrial subsidies,” or “export dependency” ignore China’s substantial contributions to the global industrial chain stability and growth, and overlook the real needs of Global South countries for energy, technology, and economic development.


A sick person doesn’t get well by forcing others to take the medicine. Those who use “economic rebalancing” to justify protectionism have nothing to gain and will only destabilize global industrial and supply chains, harm emerging sectors and hinder the world’s climate response and green transition. Practice has fully demonstrated that China’s development is an opportunity for the world. China will continue to unswervingly advance high‑level opening‑up, open the door wider for sharing development opportunities, and bring more stability and certainty to the turbulent world.


Ambassador JIANG Feng is Head of Mission of China to the AU and Representative of China to the UNECA