Tuesday, January 20, 2026

Uganda: Construction of Katonga bridge to commence in October

The Minister for Works and Transport, Gen. Katumba Wamala has revealed that construction of a new bridge at the Katonga river along the Kampala-Masaka highway will commence in October this year.

He made the revelation while responding to a matter of national importance raised by Kashari North County Member of Parliament, Hon. Basil Bataringaya, during the plenary sitting on Tuesday, 23 July 2024.

Bataringaya expressed concern that repairs on the existing bridge had been abandoned and tasked the minister to give dates by which the key trade route would be fixed.

“Last year, the Katonga bridge was swept away and closed for more than six months. Temporary measures were taken to repair this bridge, and traffic was channeled through the long Sembabule road which was inconveniencing to traders in terms of money and time,” Bataringaya said.

He urged the Works Minister to create a shorter alternative route as works on the affected bridge take shape.

“And in this case, I propose the Villa Maria-Kalungu-Masaka road,” he added.

Gen. Katumba Wamala said that the Katonga bridge was compromised due to meteorological changes which impacted the behavior of the river.

“We had to study the meteorological behaviors of that river so that we can make a new structure which is resilient and will stand the test of time. We could not rush into establishing more or less the same bridge which had been compromised,” he said.

The minister also revealed that contractor will address the challenges within Kalandazi and Lwera swamps to ensure that the section of the road is restored to meet the challenges of the truck volumes.

He also called on road users along the Kampala-Masaka highway to exercise patience as construction works on the new bridge takes place.

“I want us to understand these structures are not simple structures to do. If we do a structure in a hurry, and it gives away in a few years, it will be this same House that will put us to task. This is a very sensitive structure and so it should be done with all the caution and detail it deserves,” said Katumba Wamala.

In May 2023, the Katonga bridge was destroyed by flash floods prompting the government to create a diversion for heavy trucks to the Mpigi-Sembabule-Masaka road.

Distributed by APO Group on behalf of Parliament of the Republic of Uganda.

Hot this week

Production up, but the ‘cost’ variable weighs heavily

Production is up in 2021 for the Italian agricultural...

Luminos Fund’s catch-up education programs in Ethiopia recognized

The Luminos Fund has been named a top 10...

Well-planned cities essential for a resilient future in Africa concludes the World Urban Forum

The World Urban Forum (WUF) concluded today with a...

Private sector deemed key to unlocking AfCFTA potential

The private sector’s role is vital to fully unlock...

Why ending child marriage is key for seizing Africa’s demographic dividend

Africa’s future prosperity needs its girls… Africa is home to...

The Prosperity Gospel And The Mirage Of Real Development

Across much of the Global South, and increasingly beyond...

Why Financial Crime Risk Demands Regulation and How Africa Is Leading the Way

In the past decade, our financial systems have become...

Seven Lessons for Ethiopia Innovation Economy from Switzerland

Countries Are Evolving From Factor Driven, to Efficiency Driven...

Why Financial Crime Risk Demands Regulation and How Africa Is Leading the Way

In the past decade, our financial systems have become...
spot_img

Related Articles

Popular Categories

spot_imgspot_img